Satya Narayana Pet (S N Pet)
⚫Much work is pending on this side. Landfilling for construction of slope seen in picture no.3 was under progress. Couldn't take any pictures as there was too much traffic
🔸
#Electrificationupdate◾Towards Guntakal side
⏺️Wiring completed for both up and down lines - Pictures 5 to 16
⏺️Erection of some masts is under progress - Pictures 12 to 16
⏺️Aligned OHE poles - Pictures 13, 14 & 16
⏺️Wiring is done for two masts - Pictures 15 & 16
⏺️Erection of some OHE portals yet to be completed in goods section - Picture 16
⏺️Masts have not yet been erected in OHE portals of goods section - Picture 16
◾RVNL equipment parked in Goods section - Picture 17
◾Towards Hosapete
⏺️Aligned OHE portal - Pictures 18, 20 & 26
⏺️OHE poles with insulators - Pictures 19, 23 & 25
⏺️Masts have not yet been erected in OHE portals of goods section - Picture 19
⏺️Erection of OHE portal under progress at goods section - Pictures 22 & 23
⏺️Erection of some masts is under progress - Pictures 24 & 25
⏺️Aligned OHE poles - Pictures 21 to 26
⏺️Wiring is done for one mast - Pictures 19, 21, 22, 24, 25 & 26
⏺️Wiring under progress for two masts - Pictures 19, 21 & 22
⚫Wiring done for entire up main line i.e., track in between PF#1 & PF#2
🔸Conclusion as on March 22nd 2019:
⚫Wiring done for both up & down main lines towards both Hosapete side and Guntakal side
⚫Wiring under progress for platforms and turnouts within station premises
⚫Wiring is not started in goods section as masts have not been fixed
Pictures source: Self