From railway portal:
Barlai - Laxmibai Nagar (20.75 Km) : Balance Private land is 0.883 Ha (0.594 + 0.289) between Mangliyagaon-Laxmibainagar Private land is 0.883 Ha (0.594 + 0.289). Award Declared on 29.08.23. Possession received on 07.10.23. Work is in progress. T.W.O. of 22 days is planned. T.W.O. is under approval of HQ. TWO work involved insertion of 21 T/O & dismantling...
more... of 21 T/O at MGG & LMNR Yards TDC: 36.38 Km.- Commissioned (Karachha-Binjana-Barlai) : 20.75 Km - Dec23
please wait...Translate to EnglishYo, from the rail website:
Barlai - Laxmibai Nagar (20.75 Km): We got some private land left, about 0.883 Ha (0.594 + 0.289) between Mangliyagaon-Laxmibainagar. Award was given on 29.08.23 and we got possession on 07.10.23. The work is still going on, man. We're planning a T.W.O. of 22 days, but it's still waiting for approval from HQ. The T.W.O. work involves inserting and dismantling 21 T/O at MGG & LMNR Yards. TDC: 36.38 Km.- Commissioned (Karachha-Binjana-Barlai): 20.75 Km - Dec23.