Today's observation on Limbgaon mudkhed route :
From Limbgaon to Nanded, bridges have almost completed but only 3 to 4 km track has been laid, rest is going on.
From Nanded to Mugat, nothing is going on, no earthwork no track laying. Only bridge work on Aasna river is going on.
From Mugat to Mudkhed, earthwork almost completed except for a short patch...
more... near mudkhed station. Nearly 3 km of track is laid out of 9 km
Overall we can't expect this route to become operational any time before June. The deadline is March.