1) Tender invited for GC work between Patalpani (excl.) Ch.0000 to T1 (Indore end) Ch.7540m (NIT Cost - 261.99 Cr). (Tender opened on07.06.24 and under finalization, TDC-30.08.2024)
(2) Tender awarded for longest tunnel (T1) of 4.1Km (Ch.7540m toCh.11740m) & mobilization in progress (TDC: 31.12.26). Forest land under acquisition.
(3)...
more... Tender schedule is under preparation for GC work between Tunnel T1 (KNW end-Ch.11740m) to Rajpura T7 (Indore end - Ch. 410000m) (NIT Cost - Approx 1200 Cr ). (TDC for NIT: 30.08.24)
(4) Tender invited for GC work between Rajpura (Excluding) Ch. 41000) to Choral (excl.) Ch:49000 and including Tunnel T-14 (2.29 Km) & T-13 (1.6km ) (NIT Cost - 468 Cr). (Tender opened on 31.07.24 & under finalization.)
(5) Tender invited for GC work between Choral (incl.) CH:49000 to Muktiyara Balwara (excl.) CH:649000 Section excluding Tunnel No.14 (NIT Cost- 261.79 Cr). (Tender opened on 05.07.24, Finalization TDC-15.09.24)
(6) For Mukhtiyara Balwada- Omkareshwar (21.75 Kms) : EPC Tender awarded to M/s KEC International Limited - Gurgaon on 16.05.24.
Target Plan:
4.6 Km - Dec.'25/Feb'26 (Patalpani- Badiya)
60.5 Km - Feb.'27 (Badiya-Mukhtiyara)
20.7 Km - Jan.'26/Dec'25 (Muktiyara - Omakareshwar)
-----------------------
Dekakund-Tanda Road (15.70 Km)
Target postponed to Dec'24 as advised vide this railways letter dt. 16.05.24. CRS inspection planned on 28.12.24.
Tanda Road - Tirla (On EPC mode) (46.71 Km) : EPC tender for Package 1 (not involving Forest land) and EPC for Package 2 (After Clearance of Forest land) are under preparation. TDC : 31.12.24
Target Plan:
11.88 Km - June'24/Dec'24 (Jobat-Dekakund)
15.70 km - Oct.'24/Dec'24 (Dekakund - Tanda Road)
46.71 Km (Bal.) - Dec.'26 (Tanda Road - Tirla)